Commercial Art Program Timeline Checklist

A phase-by-phase reference from signed proposal to installed.
Prepared by PICTURE THIS FRAMING Fullerton, California
Typical single-phase program: 14 to 26 weeks (3.5 to 6 months) from signed proposal to final piece hung. The critical path is almost always moulding sourcing — lock specifications early to compress the schedule.

Phase-by-Phase Timeline

1
Discovery & Quoting
2 to 4 weeks
Share piece list, sizes, and budget. Framer matches design intent to budget with a detailed quote.
2
Specification & Sample Approval
2 weeks
Lock moulding, mats, glazing, substrates. Approve physical samples where required.
3
Art Sourcing / Licensing
2 weeks (parallel)
Designer finalizes selections; framer can assist with acquiring originals when needed.
4
Moulding & Materials Sourcing
2 weeks to 6 months
Stocked profiles ship in days; large custom orders can run 90 days to 6 months from the mill. Critical path.
5
Printing & Framing Production
1 to 10 weeks
In-house throughput: 100 large or 250 smaller pieces per week. Fine-art Epson printing on-site.
6
QC, Packaging & Crating
1 week
Inspection, cleaning, and packaging — individual cartons, pallets, or custom crates.
7
Freight to Site
1 to 2 weeks (domestic)
7 to 10 days LTL from Fullerton, CA to the Northeastern U.S. Cruise / international coordinated to ship windows.
8
On-Site Installation
Up to 30 pcs / installer / day
1 installer for ~100 pcs; 2-person crew for 500 to 1,000+ pcs. Requires ready walls and closed punch list.

Total Timeline Benchmarks by Program Type

Program Type Piece Count Realistic Total Timeline
Boutique hotel~150 pieces14 to 22 weeks (3.5 to 5 months)
Full-service hotel~500 to 800 pieces20 to 36 weeks (5 to 9 months)
Hospital / medical office~300 to 600 pieces16 to 28 weeks (4 to 7 months)
Corporate HQ / office~200 to 400 pieces14 to 24 weeks (3.5 to 6 months)
Cruise ship refurbishment1,500 to 3,500 pieces32 to 52 weeks (8 to 12 months)

Top 3 Things That Blow Up a Timeline

1. Moulding Lead Time
Large custom orders can run 90 days to 6 months from the mill. Lock specs early.
2. Slow Client Decisions
Every week added to art or spec approval is a week lost on the back end — the “done by” date rarely moves.
3. File & PM Discipline
Wrong file formats and unresolved decisions rework the schedule. Assign a clear project owner.